This open house was active from Feb 11-27, 2022. Information on this website may no longer be current. Email us for more information.
Dates are estimates and subject to change.
-
Stage 1
March-May 2022Construction along the west side of Cornelius Pass Road.
-
Stage 2, Phase 1
June 2022-August 2023Construction along east side of Cornelius Pass Road. Willamette Water Supply pipeline installation. Construction of dedicated right-turn lane on Tualatin Valley Highway.
-
Stage 2, Phase 2
July-August 2023Installation of a section of waterline across Cornelius Pass Road.
-
Stage 3
August-December 2023Final construction.